March 2003
|
DATE |
ACTIVITY |
| 03/03 | Petawatt design, Cleaner alignment |
| 03/04 | Petawatt design |
| 03/05 | Petawatt design, regen is fixed |
| 03/06 | Petawatt design, laser maintenance |
| 03/07 | Petawatt design, laser maintenance |
|
DATE |
ACTIVITY |
| 03/10 | Regen in diagnostic regime for LILAC alignment (starting 10:10 AM), petawatt design |
| 03/11 | Regen in diagnostic regime for LILAC alignment (starting 10:20 AM), petawatt design |
| 03/12 | Regen in diagnostic regime for LILAC alignment, (starting 10:30 AM), laser has been switched off at 4:30 PM due problems with chiller, petawatt design |
| 03/13 | Regen has been restored at 12 AM, LILAC alignment, petawatt design |
| 03/14 | Regen in diagnostic regime for LILAC alignment, (starting 10:30 AM), petawatt design |
|
DATE |
ACTIVITY |
| 03/17 | Regen in diagnostic regime for wavefront correction (started 10:00AM), petawatt pump alignment |
| 03/18 | Regen in diagnostic regime for LILAC alignment (started 10:00 AM), petawatt pump alignment |
| 03/19 | Regen in diagnostic regime for LILAC alignment (started 10:00 AM), petawatt pump alignment |
| 03/20 | Regen in diagnostic regime for LILAC alignment (started 10:00 AM), petawatt pump alignment |
| 03/21 | Regen in diagnostic regime for LILAC alignment (started 10:30 AM), petawatt pump power measurements (22 J in one channel) |
|
DATE |
ACTIVITY |
| 03/24 | Regen in diagnostic regime for LILAC alignment (started 10:00AM), petawatt pump energy measurements (34J in one channel). Turned off 9:00 PM. |
| 03/25 | Regen in full power regime for LILAC alignment (started 10:00AM), compressors alignment for LILAC, petawatt pump energy measurements (37J in one channel). Turned off 7:00 PM. |
| 03/26 | Regen in diagnostic regime for LILAC alignment (started 10:00AM), regen in full power regime, pulse duration measurements (25 fs) for LILAC, cleaner is on, fairing with 10 TW (started 6:00 PM), petawatt pump energy measurements (47J in one channel). Turned off 9:30 PM. |
| 03/27 | Regen in diagnostic regime (turned on 10:00 AM) for LILAC alignment (started 12:30 PM), regen in full power regime for LILAC alignment and wavefront correction (started 4:30 PM). Turned off 8:15 PM. |
| 03/28 | Regen in diagnostic regime (turned on 10:10 AM) for wavefront correction (started 3:00 PM), regen in full power (started 5:00PM). |
April
2003|
DATE |
|
||||
|
03/31 Monday |
|
||||
|
04/01 Tuesday |
|
||||
|
04/02 Wednesday
|
|
||||
|
04/03 Thursday |
|
||||
|
04/04 Friday |
|
|
DATE |
|
||||
|
04/07 Monday |
|
||||
|
04/08 Tuesday |
|
||||
|
04/09 Wednesday
|
|
||||
|
04/10 Thursday |
|
||||
|
04/11 Friday |
|
|
DATE |
|
||||
|
04/14 Monday |
|
||||
|
04/15 Tuesday |
|
||||
|
04/16 Wednesday
|
|
||||
|
04/17 Thursday |
|
||||
|
04/18 Friday |
|
|
DATE |
|
||||
|
04/21 Monday |
|
||||
|
04/22 Tuesday |
|
||||
|
04/23 Wednesday
|
|
||||
|
04/24 Thursday |
|
||||
|
04/25 Friday |
|
|
DATE |
|
||||
|
04/28 Monday |
|
||||
|
04/29 Tuesday |
|
||||
|
04/30 Wednesday
|
|
||||
|
04/01 Thursday |
|
||||
|
04/02 Friday |
|
May 2003
|
DATE |
|
||||
|
05/04 Sunday |
|
||||
|
05/05 Monday |
|
||||
|
05/06 Tuesday
|
|
||||
|
05/07 Wednesday |
|
||||
|
05/08 Thursday |
|
|
05/09 Friday |
|
|
05/10 Saturday |
|
|
DATE |
|
||||
|
05/13 Monday |
|
||||
|
05/14 Tuesday
|
|
||||
|
05/15 Wednesday |
|
||||
|
05/16 Thursday |
|
|
05/17 Friday |
|
|
DATE |
|
||||
|
05/19 Monday |
|
||||
|
05/20 Tuesday
|
|
||||
|
05/21 Wednesday |
|
||||
|
05/22 Thursday |
|
|
05/23 Friday |
|
|
DATE |
|
||||
|
05/27 Monday |
|
||||
|
05/28 Tuesday
|
|
||||
|
05/29 Wednesday |
|
||||
|
05/30 Thursday |
|
|
05/31 Friday |
|
JUNE 2003
|
DATE |
|
||||
|
06/03 Monday |
|
||||
|
06/04 Tuesday
|
|
||||
|
06/05 Wednesday |
|
||||
|
06/06 Thursday |
|
|
05/07 Friday |
|
|
DATE |
|
|
06/09 Monday |
|
||||
|
06/10 Tuesday
|
|
||||
|
06/11 Wednesday |
|
||||
|
06/12 Thursday |
|
|
05/13 Friday |
|
|
DATE |
|
||||
|
06/16 Monday |
|
||||
|
06/17 Tuesday
|
|
||||
|
06/18 Wednesday |
|
||||
|
06/19 Thursday |
|
|
06/20 Friday |
|
|
DATE |
|
||||
|
06/23 Monday |
|
||||
|
06/24 Tuesday
|
|
||||
|
06/25 Wednesday |
|
||||
|
06/26 Thursday |
|
|
06/27 Friday |
|
July 2003
|
DATE |
|
||||
|
06/30 Monday |
|
||||
|
07/01 Tuesday
|
|
||||
|
07/02 Wednesday |
|
||||
|
07/03 Thursday |
|
|
07/04 Friday |
|
|
DATE |
|
||||
|
07/07 Monday |
|
||||
|
07/08 Tuesday
|
|
||||
|
07/09 Wednesday |
|
||||
|
07/10 Thursday |
|
|
07/11 Friday |
|
|
DATE |
|
||||
|
07/13 Monday |
|
||||
|
07/14 Tuesday
|
|
||||
|
07/15 Wednesday |
|
||||
|
07/16 Thursday |
|
|
07/17 Friday |
|
|
DATE |
|
||||
|
07/21 Monday |
|
||||
|
07/22 Tuesday
|
|
||||
|
07/23 Wednesday |
|
||||
|
07/24 Thursday |
|
|
07/25 Friday |
|
July 25 - August 3 VOCATION!!!
August 2003
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
08/05 Tuesday
|
Regen in diagnostic regime, oscillator and regen alignment |
|||
|
08/06 Wednesday
|
Regen in diagnostic regime, regen in full power, 4 - pass amplifier alignment to improve a beam profile, water filters installation for chilling systems of PRO and Macho Light lasers |
|||
|
08/07 Thursday
|
Regen in diagnostic regime, regen in full power, compressor chamber alignment to make measurements of pulse duration and spectrum in 30 TW regime, water filters installation for chilling systems of Glass laser and Petawatt pump laser |
|||
|
08/08 Friday |
Regen in diagnostic regime, problems with chilling system of regen Pockels call, maintenance day |
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
08/11 Monday
|
Regen chiller maintenance, regen alignment | |||
|
08/12 Tuesday
|
Regen in diagnostic regime, regen in full power, four-pass amp. on |
|
||
|
08/13 Wednesday
|
Regen in diagnostic regime,
second order autocorrelator alignment, oscillator in Macho Light laser alignment
|
|
||
|
08/14 Thursday
|
Regen in diagnostic regime Switching-off of an electricity |
solid target alignment |
||
|
08/15 Friday |
no electricity, Gerard Mourou brought his own power generator to run ion pumps |
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
08/18 Monday |
Regen in diagnostic regime | rarified gas target alignment | ||
|
08/19 Tuesday
|
Regen in diagnostic regime, regen in full power |
rarified gas target alignment |
||
|
08/20 Wednesday
|
Regen in diagnostic regime regen in full power |
rarified gas target alignment |
||
|
08/21 Thursday
|
Regen in diagnostic regime regen in full power
|
rarified gas target alignment |
||
|
08/22 Friday |
Regen in diagnostic regime regen in full power |
firing with energy from 5 up to 15 mJ into rarified gas target |
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
08/25 Monday |
Regen in diagnostic regime, regen in full power |
firing with pulse energy up to 7 mJ into rarified gas target, the goal of the experiment is to observe electrons after noble gas atoms ionization by laser light. | ||
|
08/26 Tuesday
|
Regen in diagnostic regime, regen in full power |
firing with pulse energy up to 7 mJ into rarified gas target. No electrons has been detected. |
||
|
08/27 Wednesday
|
Regen in diagnostic regime,
regen in full power |
firing with pulse energy up to 7 mJ into rarified gas target. No electrons has been detected. |
||
|
08/28 Thursday
|
Regen in diagnostic regime, regen in full power, Macho Light laser maintenance | |||
|
08/29 Friday |
Regen in diagnostic regime, regen in full power |
firing with pulse energy up to 7 mJ into rarified gas target. No electrons has been detected. |
September 2003
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
09/01 Monday |
LABOR DAY |
LABOR DAY |
LABOR DAY
|
LABOR DAY
|
|
09/02 Tuesday
|
Regen in diagnostic regime, regen in full power, 4-pass amp. on, 2-pass amp. on. No amplification in 2-pass amp. setup because crystal position is wrong |
solid target alignment. |
||
|
09/03 Wednesday
|
Regen in diagnostic regime, 2-pass amp. crystal has been installed proper way |
solid target alignment with diode laser |
||
|
09/04 Thursday
|
Regen in diagnostic regime |
solid target alignment with diode laser |
||
|
09/05 Friday |
Regen in diagnostic regime, regen in full power, 4-pass amp. on. Bad beam profile after 4-pass has been found out. The reason is - old charging lamps in amplifier and preamplifier of Macho Light laser (4-pass pump) |
solid target alignment with diode laser |
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
09/08 Monday |
Regen in diagnostic regime, lamps in preamplifier and both amplifiers of Macho Light laser (4- pass amplifier pump) has been changed |
solid target alignment | ||
|
09/09 Tuesday
|
High voltage power supply in Regen pump (PRO laser) is broken, new one has been ordered from Spectra Physics. Macho Light laser maintenance. |
solid target alignment with diode laser |
||
|
09/10 Wednesday
|
High voltage power supply in Regen pump (PRO laser) is broken, new one has been ordered from Spectra Physics. Macho Light laser maintenance. |
solid target alignment with diode laser |
Yellow channel of petawatt pump alignment |
|
|
09/11 Thursday
|
solid target alignment with diode laser |
Yellow channel of petawatt pump alignment, the rod in yellow head has been burned |
||
|
09/12 Friday |
|
An extra rod cleaning to put instead burned one |
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
09/15 Monday |
The power supply installation into PRO amplifier , Regen in diagnostic regime, regen in full power, 4-pass on |
solid target alignment. |
|
An extra rod cleaning to put instead burned one |
|
09/16 Tuesday
|
Regen in diagnostic regime |
solid target alignment. |
New rod installation into yellow head of petawatt pump | |
|
09/17 Wednesday
|
Regen in diagnostic regime |
solid target alignment |
|
|
|
09/18 Thursday
|
Regen in full power |
drilling holes in the solid target |
|
|
|
09/19 Friday |
Regen in full power |
drilling holes in the solid target |
|
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
10/20 Monday |
Regen in diagnostic regime |
solid target alignment. |
|
|
|
10/21 Tuesday
|
Regen in full power |
drilling holes in the solid target |
||
|
10/22 Wednesday
|
Regen in full power |
drilling holes in the solid target
|
|
|
|
10/23 Thursday
|
Regen in diagnostic regime, 4 - pass amp. alignment |
|
|
|
|
10/24 Friday |
Regen in diagnostic regime 4 - pass amp. alignment , water pump in Macho Light power supply was broken |
|
|
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
10/27 Monday |
Regen in diagnostic regime |
solid target alignment. |
|
|
|
10/28 Tuesday
|
Regen in full power |
drilling holes in the solid target |
||
|
10/29 Wednesday
|
Regen in full power, new water pump installation into Macho Light power supply |
drilling holes in the solid target
|
|
|
|
10/30 Thursday
|
Regen in diagnostic regime, Regen in long pulse, 4 - pass amp. on, checking of the beam profile at the exit of 4-pass |
drilling holes in the solid target |
|
|
|
10/31 Friday |
Regen in full power |
drilling holes in the solid target |
|
November 2003
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
11/03 Monday |
Regen in full power |
drilling holes in the solid target |
|
|
|
11/04 Tuesday
|
Regen in full power |
drilling holes in the solid target |
||
|
11/05 Wednesday
|
Oscillator problems because vibration |
|
|
|
|
11/06 Thursday
|
Oscillator alignment |
|
|
|
|
11/07 Friday |
Regen in full power |
drilling holes in the solid target |
|
|
DATE |
HERCULES |
ABOVE THRESHOLD IONIZATION EXPERIMENT |
LILAC | PETAWATT |
|
11/10 Monday |
Regen in full power |
drilling holes in the solid target |
|
|
|
11/11 Tuesday |
Regen in full power |
drilling holes in the solid target |
||
|
11/12 Wednesday |
Regen in full power |
drilling holes in the solid target |
|
|
|
11/13 Thursday |
Regen in full power |
drilling holes in the solid target |
|
|
|
11/14 Friday |
Regen in full power |
drilling holes in the solid target |
|
Research Index / Hercules / Schedule of previous weeks / 2003
|
Copyright © Center for Ultrafast Optical Science, University of Michigan |
|
Maintained
by: |